| ID | Task Name | Duration | Start | Finish | Resource Names |
| 1 | XYZ, Inc. Phase I - GL, Projects, Government Portal | 25.09 days | Thu 9/20/01 | Thu 10/25/01 | |
| 2 | Structure Phase | 25.09 days | Thu 9/20/01 | Thu 10/25/01 | |
| 3 | Implementation Plan and Strategy | 25.09 days | Thu 9/20/01 | Thu 10/25/01 | |
| 4 | Perform New Customer Launch | 2.5 days | Thu 9/20/01 | Mon 9/24/01 | |
| 5 | Conduct Administrative Setup | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead[200%] |
| 6 | Order Application Software | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | PS Account Executive |
| 7 | Initiate Launch Meeting Preparation | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead |
| 8 | Perform Education Services Process | 0.5 days | Fri 9/21/01 | Fri 9/21/01 | PS Account Executive |
| 9 | Review Installation Requirements | 0.5 days | Fri 9/21/01 | Fri 9/21/01 | PS Account Executive |
| 10 | Conduct Launch Meeting | 0.5 days | Mon 9/24/01 | Mon 9/24/01 | PS Project Mgr/Tech Lead |
| 11 | Conduct Launch Termination | 0 days | Mon 9/24/01 | Mon 9/24/01 | |
| 12 | Perform New Customer Launch Complete | 0 days | Mon 9/24/01 | Mon 9/24/01 | |
| 13 | Define Project Standards and Administration | 5.21 days | Thu 9/20/01 | Thu 9/27/01 | |
| 14 | Acquire Team Work Location | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 15 | Create Project Diary | 2.53 days | Thu 9/20/01 | Mon 9/24/01 | PS Project Mgr/Tech Lead[20%] |
| 16 | Create Project Administration and Reporting Procedures | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 17 | Develop Issue Resolution Procedures | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 18 | Define Technical Project Standards | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 19 | Define Process Change Control Process | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 20 | Define Roles and Responsibilities for Project | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 21 | Create Project Plan Maintenance Procedures | 4.74 days | Thu 9/20/01 | Wed 9/26/01 | PS Project Mgr/Tech Lead[11%] |
| 22 | Define Project Standards and Administration Complete | 0.47 days | Wed 9/26/01 | Thu 9/27/01 | |
| 23 | Define Quality Assurance Process | 1.65 days | Thu 9/20/01 | Fri 9/21/01 | |
| 24 | Define Project Review and Audit Process | 0.24 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead[213%] |
| 25 | Define Project Process for Review and Audit | 0.48 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead[105%] |
| 26 | Define Project Review and Audit Frequency | 0.47 days | Thu 9/20/01 | Fri 9/21/01 | PS Project Mgr/Tech Lead[106%] |
| 27 | Define Quality Assurance Process Complete | 0.47 days | Fri 9/21/01 | Fri 9/21/01 | |
| 28 | Define Mission, Objectives, and Performance Measures | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | |
| 29 | Define Project Mission Statement | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | XYZ Project Team |
| 30 | Define Project Objectives and Performance Measures | 0.5 days | Thu 9/20/01 | Thu 9/20/01 | XYZ Project Team |
| 31 | Define Mission, Objectives, and Performance Measures Complete | 0 days | Thu 9/20/01 | Thu 9/20/01 | XYZ Project Team |
| 32 | Define Assumptions, Constraints, Risks, and Other Critical Path Projects | 1.41 days | Thu 9/20/01 | Fri 9/21/01 | |
| 33 | Define Assumptions | 0.47 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead[106%] |
| 34 | Define Constraints | 0.47 days | Thu 9/20/01 | Thu 9/20/01 | PS Project Mgr/Tech Lead[106%] |
| 35 | Define Risks | 0.47 days | Thu 9/20/01 | Fri 9/21/01 | PS Project Mgr/Tech Lead[106%] |
| 36 | Define Other Critical Path Projects | 0.47 days | Fri 9/21/01 | Fri 9/21/01 | PS Project Mgr/Tech Lead[106%] |
| 37 | Define Assumptions, Constraints, Risks, and Other Critical Path Projects Complete | 0 days | Fri 9/21/01 | Fri 9/21/01 | PS Project Mgr/Tech Lead[106%] |
| 38 | Define Project Training Plan | 2.24 days | Thu 9/27/01 | Mon 10/1/01 | |
| 39 | Define End User Training Strategy | 0.59 days | Thu 9/27/01 | Thu 9/27/01 | PS Project Mgr/Tech Lead[106%] |
| 40 | Identify Project Team Training Requirements | 0.71 days | Thu 9/27/01 | Fri 9/28/01 | PS Project Mgr/Tech Lead[106%] |
| 41 | Create Project Team Training Schedule | 0.95 days | Fri 9/28/01 | Mon 10/1/01 | PS Project Mgr/Tech Lead[105%] |
| 42 | Define Project Training Plan Complete | 0 days | Mon 10/1/01 | Mon 10/1/01 | PS Project Mgr/Tech Lead[106%] |
| 43 | Review Network Structures | 3.56 days | Thu 9/27/01 | Tue 10/2/01 | |
| 44 | Identify All Network Components to be Monitored | 0.95 days | Thu 9/27/01 | Fri 9/28/01 | PS Technical[105%] |
| 45 | Identify Components Outside of Network Operations Control | 0.95 days | Thu 9/27/01 | Fri 9/28/01 | PS Technical[105%] |
| 46 | Develop Evaluation Requirements and Metrics | 0 days | Fri 9/28/01 | Fri 9/28/01 | XYZ Technical |
| 47 | Evaluate Existing Network | 1.19 days | Fri 9/28/01 | Mon 10/1/01 | PS Technical[84%] |
| 48 | Establish Infrastructure Upgrade Plan | 0 days | Mon 10/1/01 | Mon 10/1/01 | XYZ Technical |
| 49 | Define Network Structures Maintenance Strategy | 0.95 days | Mon 10/1/01 | Tue 10/2/01 | PS Technical[105%] |
| 50 | Review Network Structures Complete | 0.47 days | Tue 10/2/01 | Tue 10/2/01 | |
| 51 | Define Technical Architecture Strategy | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 52 | Technology Assessment & System Audit | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 53 | Define Future Technical Architecture Strategy | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 54 | Define PeopleSoft Upgrade Strategy | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 55 | Identify Database Environment Requirements | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 56 | Identify Database Sizing Requirements | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 57 | Identify System Administration Requirements | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 58 | Create Technical Architecture Strategy Document | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 59 | Define Technical Architecture Strategy Complete | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 60 | Define Software Configuration Management Infrastructure | 8.41 days | Thu 9/27/01 | Tue 10/9/01 | |
| 61 | Build Software Configuration Management (SCM) team | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | PS Technical[106%] |
| 62 | Evaluate existing software development methodologies | 1.43 days | Thu 9/27/01 | Mon 10/1/01 | PS Technical[53%] |
| 63 | Perform fit/gap analysis of existing procedures with PeopleSoft methodology | 1.43 days | Mon 10/1/01 | Tue 10/2/01 | PS Technical[53%] |
| 64 | Identify and Document SCM Process Deficiencies | 1.31 days | Tue 10/2/01 | Wed 10/3/01 | PS Technical[105%] |
| 65 | Build SCM/Change Control Methodology | 0.95 days | Wed 10/3/01 | Thu 10/4/01 | PS Technical[105%] |
| 66 | Define Updates and Fixes Strategy | 0.47 days | Thu 10/4/01 | Fri 10/5/01 | PS Technical[106%] |
| 67 | Obtain third party software management products | 1.42 days | Wed 10/3/01 | Fri 10/5/01 | |
| 68 | Build Software Promotion Review and Approval Process | 0.95 days | Wed 10/3/01 | Thu 10/4/01 | PS Technical[105%] |
| 69 | Identify and Train Primary Support Resources | 1.42 days | Fri 10/5/01 | Mon 10/8/01 | PS Technical[141%] |
| 70 | Test software locking and promotion procedures | 0.95 days | Thu 10/4/01 | Fri 10/5/01 | PS Technical[211%] |
| 71 | Rollout SCM methodology | 0.47 days | Mon 10/8/01 | Tue 10/9/01 | PS Technical[213%] |
| 72 | Define Software Configuration Management Infrastructure Complete | 0.47 days | Tue 10/9/01 | Tue 10/9/01 | |
| 73 | IPSW Preparation | 2 days | Thu 10/4/01 | Fri 10/5/01 | |
| 74 | Prepare documents | 1 day | Thu 10/4/01 | Thu 10/4/01 | PS Engagement Manager |
| 75 | Copy and ship documents | 1 day | Fri 10/5/01 | Fri 10/5/01 | PS Engagement Manager |
| 76 | IPSW Workshop | 4 days | Mon 10/8/01 | Thu 10/11/01 | |
| 77 | Conduct IPSW Workshops | 4 days | Mon 10/8/01 | Thu 10/11/01 | PS Engagement Manager |
| 78 | Conduct IPSW Workshop Complete | 0 days | Thu 10/11/01 | Thu 10/11/01 | |
| 79 | Define Implementation Strategies | 3.47 days | Fri 10/12/01 | Wed 10/17/01 | |
| 80 | Define Conversion Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 81 | Define Interface Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 82 | Define Reporting Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 83 | Define Customization Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 84 | Define Workflow Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 85 | Define Web Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 86 | Define Help Desk/Knowledge Base Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 87 | Define Contingency Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 88 | Define Testing Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 89 | Define Content Management Strategy | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 90 | Define Information Architecture Strategy | 0 days | Fri 10/12/01 | Fri 10/12/01 | XYZ Technical |
| 91 | Define Implementation Strategies Complete | 0.47 days | Wed 10/17/01 | Wed 10/17/01 | |
| 92 | Create Project Team Communication Plan | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 93 | Assess Communication Requirements | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Project Team |
| 94 | Develop Communication Tools | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Project Team |
| 95 | Develop Communications Plan | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Project Team |
| 96 | Create Project Team Communication Plan Complete | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 97 | Create Organization Communication Plan | 2.36 days | Thu 9/27/01 | Mon 10/1/01 | |
| 98 | Assess Communication Requirements | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | PS Project Mgr/Tech Lead[106%] |
| 99 | Develop Communication Tools | 0.95 days | Thu 9/27/01 | Fri 9/28/01 | PS Project Mgr/Tech Lead[105%] |
| 100 | Develop Communications Plan | 0.47 days | Fri 9/28/01 | Mon 10/1/01 | PS Project Mgr/Tech Lead[213%] |
| 101 | Create Organization Communication Plan Complete | 0.47 days | Mon 10/1/01 | Mon 10/1/01 | |
| 102 | Create High-Level Project Plan | 3.2 days | Thu 10/18/01 | Tue 10/23/01 | |
| 103 | Develop High-Level Project Plan | 3.2 days | Thu 10/18/01 | Tue 10/23/01 | PS Project Mgr/Tech Lead[125%] |
| 104 | Create High-Level Project Plan Complete | 0 days | Tue 10/23/01 | Tue 10/23/01 | |
| 105 | Define Project Scope | 4 days | Fri 10/12/01 | Wed 10/17/01 | |
| 106 | Define Application Functional Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 107 | Define Organizational Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 108 | Define Conversion Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 109 | Define Interface Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 110 | Define Reporting Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 111 | Define Customization Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 112 | Define Workflow Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 113 | Define Technical Architecture Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 114 | Define Web Scope | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[83%] |
| 115 | Identify Future Project Considerations | 3 days | Fri 10/12/01 | Tue 10/16/01 | PS Project Mgr/Tech Lead[8%] |
| 116 | Review Project Scope with Sponsor | 1 day | Wed 10/17/01 | Wed 10/17/01 | PS Project Mgr/Tech Lead[25%] |
| 117 | Define Project Scope Complete | 0 days | Wed 10/17/01 | Wed 10/17/01 | |
| 118 | Assess Business Needs and Impact | 7 days | Thu 9/27/01 | Mon 10/8/01 | |
| 119 | Obtain Application Architecture and Review | 1 day | Thu 9/27/01 | Fri 9/28/01 | PS Functional |
| 120 | Prepare for Needs Assessment Sessions | 3 days | Fri 9/28/01 | Wed 10/3/01 | PS Functional |
| 121 | Conduct Needs Assessment Sessions | 3 days | Wed 10/3/01 | Mon 10/8/01 | PS Functional |
| 122 | Document and Analyze Needs Assessment Results | 2 days | Wed 10/3/01 | Fri 10/5/01 | PS Functional |
| 123 | Identify Potential Customization Requirements | 1 day | Thu 10/4/01 | Fri 10/5/01 | PS Functional |
| 124 | Assess Business Needs and Impact Complete | 0.47 days | Fri 10/5/01 | Fri 10/5/01 | |
| 125 | Hardware Capacity Planning | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 126 | Identify and Capacity Plan Hardware Environment(s) | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 127 | Define Hardware Capacity Planning Maintenance Strategy | 0 days | Thu 9/27/01 | Thu 9/27/01 | XYZ Technical |
| 128 | Hardware Capacity Planning Complete. | 0.47 days | Thu 9/27/01 | Thu 9/27/01 | |
| 129 | Publish Project Charter | 0 days | Tue 10/23/01 | Tue 10/23/01 | |
| 130 | Assemble Deliverables Included in Charter | 0 days | Tue 10/23/01 | Tue 10/23/01 | XYZ Project Team |
| 131 | Distribute Charter to Steering Committee | 0 days | Tue 10/23/01 | Tue 10/23/01 | XYZ Project Team |
| 132 | Publish Project Charter Complete | 0 days | Tue 10/23/01 | Tue 10/23/01 | |
| 133 | Quality Review Check Point - Implementation Plan and Strategy | 1.89 days | Tue 10/23/01 | Thu 10/25/01 | |
| 134 | Review Project Deliverables for activity group(s) | 0.95 days | Tue 10/23/01 | Wed 10/24/01 | PS Project Mgr/Tech Lead[53%] |
| 135 | Review Project Plan and resources | 0.95 days | Tue 10/23/01 | Wed 10/24/01 | PS Project Mgr/Tech Lead[53%] |
| 136 | Review Project Processes | 0.95 days | Tue 10/23/01 | Wed 10/24/01 | PS Project Mgr/Tech Lead[53%] |
| 137 | Review statement of service and current scope | 0.95 days | Tue 10/23/01 | Wed 10/24/01 | PS Project Mgr/Tech Lead[53%] |
| 138 | Document Project Review Findings | 0.47 days | Wed 10/24/01 | Wed 10/24/01 | PS Project Mgr/Tech Lead[53%] |
| 139 | Quality Review Check Point Complete | 0.47 days | Wed 10/24/01 | Thu 10/25/01 | PS Project Mgr/Tech Lead[53%] |
| 140 | Implementation Plan and Strategy Complete | 0 days | Thu 10/25/01 | Thu 10/25/01 | |